Skip to main content
CCW Commissioning Code W: Water distribution systems (2010)
Back To All Knowledge Items

CCW Commissioning Code W: Water distribution systems (2010)

Standard Rate
£80.00  +VAT
Member Rate
FREE
Download
Standard Rate
£100.00  +VAT
Member Rate
£50.00  +VAT
Purchase

Commissioning of buildings and building services is vitally important to the safe and energy efficient operation of buildings but it is not always carried out — or carried out systematically. The effective operation of any water system is dependent on satisfactory circuit balancing and commissioning. This in turn requires adequate attention to commissioning requirements during the design of the system, and a clear specification of requirements.

CIBSE Commissioning Codes set out clearly and systematically the steps required to commission buildings and building services in a proper and timely manner. This key step in the life of the building enables the system to operate as it was designed to do, and, coupled with good maintenance practice, helps provide building occupiers with a safe, good quality, comfortable internal environment delivered energy efficiently.

This edition of Commissioning Code W is based on the 1994 edition. The revision reflects the introduction of requirements for commissioning into Part L of the Building Regulations. The opportunity has also been taken to reflect the growing awareness that many key decisions relating to the construction process are taken in the very early stages of a project. The Code therefore gives the strongest encouragement to designers and clients to consider commissioning and to seek suitably qualified specialist input at the earliest stages of a project.

CIBSE Commissioning Code W represents current standards of good commissioning practice presented in the form of recommendations and guidance which are generally accepted in the building services industry. The Code acknowledges that it may be applied in a variety of contractual frameworks. Users will need to ensure that the use of the Code is considered when contractual arrangements are being made, to ensure that the recommendations of the Code are not in conflict with those of the contract.

Contents

W0 Introduction

W0.1 Scope

W0.2 Purpose

W0.3 Summary of commissioning requirements

W0.4 The importance of commissioning

W0.5 Other guidance

W0.6 Definitions

W0.7 Specification

W0.8 Inspection

W0.9 Commissioning records

W0.10 Responsibility

W1 Safety issues

W1.1 Legislation

W1.2 Good practice

W2 Design for commissionability

W3 Specification issues

W4 Commissioning project management

W5 Pre-commissioning

W5.1 Objective

W5.2 State of the system

W5.3 Checks before filling

W5.4 System filling and venting

W5.5 System flushing and cleaning

W5.6 System checks

W5.7 Static completion records

W6 Setting pumps to work

W6.1 Pressurisation sets

W6.2 Checks before pump start

W6.3 Initial run

W6.4 Further venting

W6.5 Completion certification

W7 Balancing and regulating water flow rates

W7.1 Objective

W7.2 Flow rate measurement tolerances

W7.3 Basis of proportional balancing

W7.4 Pump shut-off head test

W7.5 Preliminary flow rate check

W7.6 Constant volume systems

W7.7 Variable volume systems

W7.8 Balancing by compensated method

W7.9 Regulation by temperature balance

W7.10 Commissioning certification

W8 Evaluation and witnessing of commissioned systems

W8.1 Objective

W8.2 Witnessing arrangements

W8.3 Duties of witnessing agent

W8.4 Commissioning documentation


Appendix WA1: Design

Appendix WA2: Flow measurement and regulation

Author: Chris Parsloe (Parsloe Consulting)

Steering Committee: Bryan Franklin (chair); Mike Campbell (AECOM); Roger Carlin (Ashford Environmental Services Ltd.); Luke Collier (Belimo Automation UK Ltd.); John Coppin (Commissioning Specialists Association); Peter Davey (Balfour Beatty Engineering Services); Terry Dix (Arup); Terry Dodge (Raxcrest Valves Ltd.); Chris Driscoll (SES Ltd.); Matthew Dunk (Frese Ltd.); Lars Fabricius (SAV UK Ltd.); Lee Hansard (Wates Interiors); Andy Lucas (Crane); Bill McCluskey (Sutton Group); Gerry McGilley (Siemens Building Technologies); Peter McMahon (Barfield Services Limited); Malcolm Moorby (Crown House Ltd.); George Moss (Burgess Group); Peter Rees (Tour and Andersson Ltd.); Nick Till (Banyard Group); Brian Townsend (End Systems Ltd.); Nick Ward (Commtech Ltd.); Paul Wightman (Danfoss Ltd.)

Project coordinated by Hywel Davies (CIBSE), Anne King (BSRIA) & Claire Ruston (CIBSE)

Share this page